Friday, July 10, 2009

The Second Floor


Here workers place the decking for the second floor of the Karen H. Huntsman Library. There will be one more floor about this one by the time they finish. The steel work should be completed by the end of next month.

The Basement

Here is a shot of the basement in the Karen H. Huntsman Library with the circular staircase in the background.

The Circular Staircase


This is a shot of the contractors at work putting together the frame for the circular staircase in the Karen H. Huntsman Library. This staircase leads from the basement up all the way up to the third floor and will have a beautiful glass handrail. The four floors of open space will be a nice little “wow” in the library. Layton Construction tells us 1/3 of the library is completed and they are on schedule for a June completion.